Step-by-step Guide

Not every floor layer requires the same reinforcement. The structural slab, the ground-bearing floor, and the thin screed must be differentiated, and the application of mesh and its parameters must be determined according to the design or specified flooring system. The following guidelines concern installation organization, not the independent design of the floor.

Why is reinforcing mesh so important?

Role of floor reinforcement:

  • The mesh may limit the width of cracks formed due to shrinkage and loads.
  • It does not remove concrete shrinkage or the causes of substrate settlement.
  • Its effectiveness depends on parameters, placement, overlaps, movement joints, and the execution of the layer according to the design.

A correctly laid mesh is the basis for a durable, safe, and load-resistant floor.

Step 1: Substrate Preparation

  1. Leveling and compacting the ground – preferably mechanically, using a compactor.
  2. Laying insulation layers:
  • Geotextile – filter separating the ground from the bedding layer.
  • Sand or gravel bedding – thickness adjusted to ground conditions.
  • Construction film or insulation mat – protects the concrete from rising moisture from the substrate.
  • Expanded polystyrene (EPS, optional) – for floors requiring thermal insulation.

Step 2: Choosing and preparing reinforcing mesh

  • Mesh type: Steel mesh made of ribbed bars with a diameter of Ø4–Ø8 mm is most commonly used. Standard openings have dimensions of 10x10 cm or 15x15 cm.
  • Sheet dimensions: Usually 2x3 m or 2x5 m.
  • Cutting: If necessary, the mesh can be cut with an angle grinder or reinforcement wire cutters.

Step 3: Laying the reinforcing mesh

For the reinforcement to work effectively, it must be positioned correctly inside the screed cross-section – it cannot lie directly on the bottom.

Rules for correct installation:

  • Use stable reinforcement spacers and supports to keep the mesh in the position specified in the design.
  • Do not leave the mesh directly on the film or insulation if it is intended to be covered by concrete.
  • The length of the overlaps and the method of execution result from the documentation; one opening is not a universally sufficient length.
  • Maintain the specified concrete cover, gaps, and details near walls, openings, and movement joints.

Step 4: Pouring the concrete

  • When laying the mixture, do not allow the mesh to shift or the supports to be damaged.
  • The class and properties of the concrete are chosen according to the purpose of the element and the environmental conditions. C20/25 is not a universal minimum for every floor.
  • The method of compacting and leveling must correspond to the mix and the execution technology.

Step 5: Concrete curing

To prevent cracking in the screed during the first days:

  • Start protection against excessive drying in accordance with the construction technology.
  • The method and time of curing are chosen according to the mix, temperature, humidity, and execution requirements.
  • Plastic sheeting, moist curing or curing compounds are used when they are appropriate for the specific solution and subsequent layers.

Most common mistakes – what to avoid?

Errors include: incorrect mesh placement, lack of appropriate supports, overlaps not consistent with the design, omitted movement joints, and insufficient curing. Preparation and possible wetting of the substrate are performed according to the construction technology. There is no general rule mandating the wetting of every film before concreting.

Summary

Properly laying the reinforcing mesh is a key stage that determines the durability of the floor. Thorough substrate preparation, appropriate selection of the mesh, and its correct securing are an investment in durability and safety.

If you have doubts, it is worth consulting a contractor or a civil engineer – correcting errors after the screed has been poured can be costly and time-consuming.

Do you need materials for your project?

Send the type of steel, dimensions, and quantities. We will check availability and prepare a quote.

Ask about steel